Route 29 Sinkhole Remediation Project

East Whiteland Township Work Area

Allen Underkofler
Morehall Road, south of Yellow Springs Road — a sinkhole-prone area.

Description

This project involves the reconstruction of a portion of Route 29 (Morehall Road) in East Whiteland Township, Chester County, to correct existing sinkhole and pavement subsidence issues. The project work area is located along Route 29 (Morehall Road) between the Pennsylvania Turnpike ramps and the intersection of North Atwater Drive/General Warren Boulevard.

Reconstruction activities are driven by a history of reoccurring sinkholes located along this stretch of highway. The intent of the project is to minimize future sinkhole problems by constructing geotechnical treatments and roadway drainage improvements to prevent surface water infiltration and provide structural support to the roadway. The purpose of the project is to provide a safe and efficient roadway while decreasing future maintenance costs and traffic impacts associated with sinkholes.

Phasing

Allen Underkofler
Approaching the Pennsylvania Turnpike E-ZPass ramps

The project phasing has been developed to reduce the overall duration of construction and to minimize impacts to the traveling public. Short term lane closures off-peak hours will be required while long term temporary lane closures will be required for much of the roadway reconstruction during the summer months when traffic volumes are the lowest and schools are not in session.

The phasing will occur as follows (dates may be slightly adjusted due to weather conditions):

Pre-Stage:
Starting February 23rd, 2018, temporary work zone messaging signs will be placed at strategic locations in and around the general project area. This signing will communicate work zone preparation start of work dates and construction activities. Preparation work with short-term daily lane closures (during off-peak hours) will occur during Spring 2018 (currently scheduled to begin on March 5th with nighttime lane closures occurring on March 6th and 7th to set temporary traffic controls). Other pre-stage work will involve pavement and drainage improvements along the southbound shoulder, as well as the relocation of underground utilities. The current traffic lane configuration will be maintained during AM and PM peak travel hours for this phase of construction. After this phase of construction is complete, temporary pre-stage conditions may be maintained or the roadway will be returned to its existing conditions until the subsequent stages of construction begin in Summer 2018.

Stage 1:
Beginning on June 8th, 2018, Stage 1 construction work will commence. This work will include excavating and rebuilding the northbound travel lanes while performing sinkhole remediation work and other geotechnical treatments. During this phase of construction, only one lane of travel in each direction will remain open within the work zone. Temporary work zone messaging will be adjusted in the surrounding roadway network to communicate construction activities and expected traffic delays to the traveling public. Throughout construction, various traffic control methods will be implemented to minimize traffic congestion. These methods include traffic signal retiming, message boards, local police assistance, and temporary flaggers. Stage 1 construction activities are scheduled to be completed by mid-July 2018.

Stage 2:
Beginning mid-July 2018, Stage 2 construction work will commence. This work includes excavating and rebuilding the southbound travel lanes while performing sinkhole remediation work and other geotechnical treatments. During these construction activities, two northbound travel lanes will be maintained while the southbound travel lanes will be reduced to one within the work zone. Temporary messaging signs will be adjusted prior to Stage 2 work to inform drivers of the change in traffic control patterns and work area delays. Throughout Stage 2 construction activities, various temporary traffic control methods will be implemented to minimize traffic congestion (as outlined under Stage 1). All construction activities that create significant temporary traffic impacts are scheduled to be completed prior to the end of August 2018.

Source: Brett Grove, P.E., Traffic Planning and Design, Inc. www.TrafficPD.com

Project Updates

April 14, 2018

Allen Underkofler
Southbound lane diverted.

May 25, 2018 – PennDOT Update

Weekday lane closures are scheduled next week on Route 29 (Morehall Road) in East Whiteland and Charlestown townships, Chester County, for construction activities related to an improvement project to reconstruct a portion of the highway between the Pennsylvania Turnpike Interchange and North Atwater Drive/General Warren Boulevard, the Pennsylvania Department of Transportation (PennDOT) announced today.

Under this improvement project. crews are working to correct existing sinkhole and pavement subsidence issues. The project is scheduled to be completed in fall 2018.

The work schedule is:
  • Wednesday, May 30, from 9:00 AM to 3:00 PM, a right lane closure is scheduled on northbound Route 29 (Morehall Road) between Flat Road/Atwater Drive and Yellow Springs Road;
  • Thursday, May 31, from 9:00 AM to 3:00 PM, a right lane closure is scheduled on southbound Route 29 (Morehall Road) between Yellow Springs Road and Flat Road/Atwater Drive; and
  • Friday, June 1, from 9:00 AM to 3:00 PM, a right lane closure is scheduled on northbound Route 29 (Morehall Road) between Flat Road/Atwater Drive and Yellow Springs Road.

Motorists are advised to allow extra time when traveling through this work zone because slowdowns will occur during construction. The contractor's schedule is weather dependent.

PennDOT is working to minimize future sinkhole problems by constructing geotechnical treatments and roadway drainage improvements to prevent surface water infiltration and provide structural support to the roadway.

Allan A. Myers, LP, of Worcester, Montgomery County, is the general contractor on the $2,592,555 project, which is financed with 100 percent state funds.

For more information on projects occurring or being bid this year, those made possible by or accelerated by Act 89, or those on the department’s Four and Twelve Year Plans, visit www.projects.penndot.gov.

A list of weekly road restrictions and PennDOT maintenance operations in the five-county Philadelphia region is available by visiting the District 6 Traffic Bulletin at www.penndot.gov/District6.

Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 860 traffic cameras.

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website.

Updated: May 29, 2018