Charlestown Township Road Base Repair and
Resurfacing Project 2011
Dan Malloy Paving provided the following schedule, which is subject to slight
changes due to inclement weather.
Road |
Start Date |
Completion Date |
Approx. Duration |
Dickson, Tranquility,
and Theresa Drives |
7/21/11 |
7/29/11 |
5 - 7 days |
Union Hill Road |
7/27/11 |
8/3/11 |
3 - 5 days |
Hilltop Road |
7/25/11* |
8/5/11 |
4 - 5 days |
Pickering Creek Rd |
7/27/11* |
8/19/11 |
5 - 10 days |
*Early start on these roads would involve completing pipe crossing repairs
and minor base repairs.
We appreciate your patience and cooperation this summer while we work on these roads
Posted: July 5, 2011.